Dev UpdateRDK-M/L&T-Shashank

Update - 17-10-2018

  • Was compiling WPE OpenCDM and generated libraries/bins required for WPE-Webkit

  • Now the new approach would be using the wpeframework from the 2017/07/28 branch and enabling the open cdm

  • Bart wants to check with Glee on Licencing & providing the Playready for the RDK community

  • Meanwhile we shall proceed with clearkey DRM module for validation
  • Shashank able to get the operator reference app in R-Pi and navigate the Apps
31-Oct-2018In-Progress
Wiki Page CreationRDK-M/L&T-Raj

Update - 17-10-2018

  • Need to send the list of accessible and non accessible links towards the LGI source code to Bart
  • Create an separate wiki page to capture the status reports and other activities related to LGI-Platform team work
NA22-Oct-2018In-Progress
Operator Reference AppRDK-M/L&T/LGI

Update - 17-10-2018

  • We shall share to the internal L&T audiences who are interested in developing applications on operator Ref App but not L&T external
  • The changes done in Operator Ref App need to be informed to LGI
  • LGI is looking on the licensing options for open sourcing the operator ref app
NANAIn-Progress
General InfoRDK-M/L&T/LGI

Update - 17-10-2018

  • Offshore team would be on holidays from 18-10-2018 to 19-10-2018
  • Bart would be travelling to Atlanta next week and we shall communicate with him on ET Zone