Engineer Name | Total sprint velocity in days (10 days) [A] | Holiday (1 day) [E] | Planned Leave [B] | Unplanned Leaves [F] | Default Velocity in days [A-B-E] | Backup Velocity in days for adhoc requests(1 days), If no adhoc requests this 1 days to be spent for a new Jira [C] | Scrum related activities(only for Scrum Master), Default 5 days and 1 day for individual contributor for their scrum activities [D] | Net capacity in days [A-B-E-D] |
---|---|---|---|---|---|---|---|---|
Sowmya | 10 | 0 | 0 | 10 | 0 | 5 | 5 | |
Rosna | 10 | 0 | 0 | 10 | 0 | 5 | 5 | |
Philip | 10 | 0 | 0 | 10 | 1 | 1 | 9 | |
Vijith | 10 | 0 | 0 | 10 | 1 | 1 | 9 | |
Venkat | 10 | 0 | 0 | 10 | 1 | 1 | 9 | |
Balaji | 10 | 0 | 0 | 10 | 1 | 1 | 9 | |
Heam | 10 | 0 | 0 | 10 | 1 | 1 | 9 | |
Rajapriya | 10 | 0 | 0 | 10 | 1 | 1 | 9 | |
Shilpa | 10 | 0 | 0 | 10 | 0 | 1 | 9 | |
Rathi | 10 | 0 | 0 | 10 | 1 | 1 | 9 | |
Fryderyk | 10 | 0 | 0 | 1 3 | 9 | 1 | 1 | 8 |
Arthur | 10 | 0 | 0 | 10 | 1 | 1 | 9 | |
Total Team Velocity | 120 | 0 | 0 | 119 | 9 | 28 | 99 |
...