Engineer Name 

Total sprint velocity in days

(10 days) 

[A]

Holiday

(1 day)


[E]

Planned Leave

[B]

Unplanned 

Leaves

[F]

Default Velocity in days

[A-B-E]

Backup Velocity in days for adhoc requests(1 days), If no adhoc requests this 1 days to be spent for a new Jira

[C]

Scrum related activities(only for Scrum Master), Default 5 days and 1 day for individual contributor for their scrum activities

[D] 

Net capacity in days

[A-B-E-D]

Sowmya 1011
8044
Rosna1011
8044
Philip1011
8117
Vijith/Dinesh1011
8117
Venkat1012
7116
Balaji101118117
Heam101425114
Rajapriya10105.59118
Rathi101019118
Fryderyk1000Didnt work10119
Shilpa1014
5114
Harshini*1012
7113
Naveen*1012
7113
Pragada*1012
7113
Sathish*1012
7113
Total Team Velocity1501417
119132186

...