Team Capacity - 

Engineer Name 

Total sprint velocity in days

(10 days) 

[A]

Holiday

(1 day)


[E]

Planned Leave

[B]

Default Velocity in days

[A-B-E]

Backup Velocity in days for adhoc requests(1 days), If no adhoc requests this 1 days to be spent for a new Jira

[C]

Scrum related activities(only for Scrum Master), Default 5 days and 1 day for individual contributor for their scrum activities

[D] 

Net capacity in days

[A-B-E-D]


















































































Sprint Planning Bug Tickets/User Stories :

Engineer NameTicket NumberTitle of the ticketBug ticketUser StorySupport Planned EstimateActual EffortCommentsUpdate on thisStatus
SowmyaBCM72180-425Validation on OCIBundle and code push
Y
2



SGMM393-159WebProcess is unresponsive and crashingY